December 7, 2017 |
Public meeting at Christ Community Church in Huntersville |
|
NCDOT met twice with the Alexander Chase community and twice with the Cooke family regarding preliminary design |
September, 2019 |
Project design finalized; no additional design changes will be made. |
2019 |
Right-of-Way acquisition begins. |
2020 |
Utility relocation begins |
2022 |
Construction begins (start delayed due to COVID-19) |