Catawba/US 21 Dual Round-about (C-5621)

C-5621_Catawba_21

Overview

Since 2016, NCDOT has been working with the Town and nearby neighborhoods and businesses to design intersection improvements for the Catawba Avenue/US 21 corridor. Pictured above is the solution, which will prohibit left-turns from Catawba Avenue. Travelers going west on Catawba and want to head south on US 21 will need to utilize the round-about north of Catawba to get to US 21. Travelers going east on Catawba and want to head north on Holiday Lane will need to utilize the round-about south of Catawba to get to Holiday Lane. 

Schedule

Date Activity
2020 Original construction date
2021 Right-of-Way acquisition and utility relocation
2023 Anticipated new construction date 

More Information

For more information, visit the Proposed Intersection Improvements at US 21/Catawba Avenue page on NCDOT's website.