W. Catawba Phase 2

W. Catawba P2 Opens in new window

Overview

It will come as no surprise to our residents that current traffic volumes exceed the capacity of the 2.7-mile stretch of West Catawba Avenue from Sam Furr Road (N.C. 73) north to Jetton Road. Fortunately, widening this stretch of road is an NCDOT approved project. 

Schedule

Date Activity
2021-2024 Right-of-way and utility relocations. Project design has been finalized; no additional design changes will be made. 
2024-2027
Construction.

More Information

Additional information on this project may be found on NCDOT's website.